Kodar | November 30, 2022
In 45 days, we completed the assembly, including the construction of the foundation and the erection of the steel structure, of the anemometer three-band lattice steel column with a height of H=110.60m. The object is of a temporary nature and is being carried out in order to install equipment for measuring wind direction and speed, temperature and air density at...